Litigation Pertaining to Asbestos Contracting
Differing Site Condition Claims, John Wiley & Sons, 1992. By John E. Osborn
Section 13.1 Asbestos Abatement Examples
Strategies set out by owners and property managers most
often determine whether and to what extent there will be a contest over
differing site conditions.
Even before a minute of analysis goes into the planning of
a project, the budget and the experience of the owner, together with the time
schedule within which the asbestos abatement work must be completed, will
help foretell whether the owner is likely to face a claim for differing site
conditions. If the owner wants the job done cheaply, is in a rush, and is
ignorant of the risks involved in asbestos abatement, there is a very good
chance that a pattern leading to a differing site conditions claim will be set
early on.
Following are three examples that illustrate changed
conditions or differing site conditions claims that could have been avoided
or limited. The remainder of the chapter provides an agenda for avoiding
these expensive pitfalls.
Example 1
A 12-story office building is about to be demolished so
that the owner can construct a new building on the property. A great deal of
attention has been placed upon the new structure, and a schedule for
demolition, construction, and occupancy has been set.
Now the focus is on demolition. Under local governmental
requirements, the asbestos in the building must be removed before demolition.
The owner hires an environmental consultant who will design the asbestos
abatement, make an award to the asbestos abatement contractor, and oversee
contract administration for the abatement.
The owner urges the environmental consultant to undertake
the project on a turnkey basis, in which the consultant takes full responsibility
for the completion of the abatement, from design through final sign-off.
The compensation for the entire project is to be included
in the bid the consultant places along with the contractor. The owner expects
the contractor to be a subcontractor to the consultant.
The consultant refuses to enter an agreement to act as a
turnkey contractor for the entire project and enters a contract with the
owner under which the consultant will design and administer the abatement
project. The consultant also agrees to assist the owner in choosing an
abatement contractor.
The consultant advises the owner that a mere visual
inspection of the premises, which might be adequate in a renovation project,
is not good enough here, as every bit of asbestos (which could be left alone
if this were a renovation) will be found as the building is being torn down.
Clearly, the cost and delay will be greater if the asbestos is found during
the job rather than pre-bid.
The consultant explains that destructive testing must be
undertaken. (Destructive testing is the process of spot checking by taking
apart the building components to determine conditions present. It can be done
in preparation for demolition, renovation, or construction.) Reluctantly, the
owner agrees to the additional expense for this testing, but only to the
extent of examining "typical conditions" on each floor. A design is
developed based upon the typical conditions, and the work is opened for bids.
The bid is awarded to an asbestos abatement contractor on
a lump-sum price, and the contractor begins work. As soon as the abatement is
begun, it is clear that in the building, which had been occupied by many
different types of business tenants over the years, had no such thing as
"typical conditions." On some floors, the tenants had removed the
vinyl asbestos floor tile and replaced it with carpeting; on other floors,
the vinyl asbestos tile had been covered with carpet. On some floors, the
column covers had been taken apart and asbestos pipe covering had been removed,
while on other floors the asbestos pipe covering remained. On some floors, no
asbestos ceiling tile was evident, as it had been covered by other ceiling
tile without asbestos, while on other floors, the asbestos-containing ceiling
tile had been removed before the new tile was installed.
As it is discovered that, in each instance, conditions are
not as "typically" shown on the contract drawings, the project is
stopped, and a meeting is called to discuss how much additional compensation
the contractor is to receive for abating the asbestos it has located that is
beyond what was anticipated.
The contract provided that the contractor was entitled to
be paid additional amounts if changed conditions were encountered.
Ultimately, extra compensation was agreed to, and the asbestos abatement was
completed. Although the price paid to the contractor was reasonable, the
owner did not have the advantage of the bargain prices it would have received
as a part of a lump-sum bid.
How the problem could have been avoided.
The owner could have derived a better bargain had it
chosen to investigate the premises further. This would have required further
payment to the environmental consultant, probably including destructive
testing on each floor. This way, the contract documents would have been
complete, and the contractor's original price would have been complete.
Another solution owners sometimes choose is to include a
clause making the contractor responsible for changed conditions when
encountered.
This approach is always a problem, as it will cause the
contractor to build in a continge..ncy to cover unknowns. If the changed
condition is significant enough, the owner may have no choice but to make
additional payment to the contractor to avoid pushing the contractor into
default or bankruptcy.
Example 2
A company is about to refinance its corporate
headquarters, move out of New York,
and then rent out the office space in that headquarters. Before the
refinancing can take place, the lender for the company requires that a Phase
I site assessment (a preliminary survey of site conditions that does not
include probing into building components) take place and that any asbestos in
fair or poor condition be removed.
The company's finance director negotiates the agreement
with the environmental consultant to perform the Phase I assessment, and
provision for destructive testing on floors 2, 11, 12, 22, 34, and 37 is
made. The areas for destructive testing are set by the finance director, who
indicates that they should provide a "representative sample" of the
building conditions (but in fact they were chosen to keep the consultant from
finding asbestos).
Once the visual inspection is complete, the environmental
consultant writes a report that is used as a basis for obtaining a bid from
an asbestos abatement contractor. The study, which becomes a part of the bid
documents in its entirety, shows that it is only in certain portions of the
structure that spray-on fireproofing is found in the building, and that there
is no asbestos pipe covering on the heating piping that serves the building.
A contractor is retained based upon a lump-sum price to
"remove all asbestos" in the building. The bid is based upon the
findings of the consultant rather than on a full set of plans and
specifications.
Once work is begun on the spot removals indicated to be
necessary in the report, it becomes clear that there is spray-on fireproofing
throughout the building and that the heating pipes, except on certain
recently renovated floors, have asbestos-containing pipe covering.
The contractor and owner meet to resolve how to proceed.
Although the negotiations progress in a reasonable fashion, the price is no
bargain for the owner.
How the problem could have been avoided.
Once again, a greater investment in the efforts of the
environmental consultant would have allowed the owner to obtain a more
accurate bid. In both cases, had the owner kept better records on the
'as-built' conditions of the building and disclosed these records to the
consultant, there would have been no changed condition claim.
Example 3
A financial institution is eager to set up a center that
will serve as a flagship for marketing a new financial product. An elaborate
retail storefront operation will be built in a prime location to house this
effort.
Although the institution already occupies the space to be
used for the new center, regulations governing asbestos were instituted since
the date of the last renovation. A filing must be made before further
renovation is undertaken, certifying that the asbestos will be removed as
part of the work.
Speed is critical in this process: the center must be
opened within three months to confide with advertising during the tax season,
when the product will be sold. To further complicate matters, the company
does not want to close the site's retail use until a week before the asbestos
abatement is to take place. This is significant because, although the
asbestos consultant has access during off hours for visual inspection, there
is no opportunity for the abatement contractor to do destructive testing
before the bid. A lump-sum agreement is preferred because management has a
set budget for the entire renovation. Although the contractor's bid must come
in well before the existing use of the space ceases and the contract calls
for the contractor to be fully familiar with the premises and to "visit
the site" beforehand, this clause is not meaningful because the
contractor is not provided access at all during the bid period. Also note
that the retail space is located in an arcade/terminal structure that is
below grade at one end of the retail space.
The lump-sum bid comes in from the four contractors
solicited. The bids range from a low bid of $800,000 to a bid of $1,250,000.
The project is commenced by the low bidder on a fast-track schedule and is
just as abruptly stopped when (1) ducts above the space are found to be
covered with asbestos; (2) a wall built over 100 years ago has holes in it
that allow air to escape to the street (the wall is also covered by
asbestos); and (3) trestles that compose part of the below-grade portion of
the premises are partially coated, apparently inadvertently, with spray-on
fireproofing and must be abated (which will be a slow and expensive process).
Negotiations take place to determine the pricing for the
newly discovered components of the project. Once again the contractor and
owner resolve the issue and the project is kept on target.
How the problem could have been avoided.
Further owner expenditures on the environmental consultant
investigation and better owner research of its own records would have saved a
significant amount of expense. Hasty planning required to keep a project on
schedule and acceleration of the work are costly items.
Section 13.2 Defining the Claim: Responsibility and
Liability
A developer once said, "Building a high rise, once
you have done one, is not a challenge; you tell me how many floors, and I can
tell you how much it should cost. It is really just 'cookie cutter'
work."
This is certainly not the case in renovation work. As
urban areas have embarked upon restoring office buildings, housing stock,
zoos, airports, skating rinks, train stations, and brownstones, the cost of
doing so has been almost impossible to determine. One cannot know the result
of a few hundred years of use, interim renovation, weathering, and decay
unless the building is torn down and thoroughly checked.
Even the seasoned architect or engineer has learned not to
speculate about the condition of the structural beams or the steel girders
that have not been seen by anyone still living. The plans that show what is
inside or behind a wall also may be outdated or inaccurate, if they can be
found at all.
Issues of responsibility and liability make estimating the
asbestos project even more of a problem. Among the architect, the owner, the
general contractor, the environmental consultant, and the demolition
contractor, no one wants to admit responsibility for overseeing the asbestos
abatement. In some cases, regulatory constraints that must be met in connection
with abating asbestos may dictate who will take on overall responsibility for
the task. However, in other instances no one person is clearly in charge of
asbestos abatement. This can present the biggest problem for all concerned.
This reluctance to take on responsibility for asbestos
abatement is fairly recent. In the mid 1980s, there was an initial surge of
interest in becoming an asbestos abatement contractor because the profit
margin was seen to be substantial. As the construction industry has become
more familiar with asbestos management, profit margins have narrowed, and the
willingness to take risks has dwindled.
For the architect, errors and omissions (malpractice)
insurance specifically excludes environmental risks. The design professional
or environmental consultant who is eligible for errors and omissions
insurance for the asbestos project can purchase it, although it is expensive.
Generally, in the beginning, when it came to asbestos
abatement, the major participants in the construction process - design
professionals, construction managers, and contractors - lacked expertise and
insurance. Although risk management experts would certainly have advised
against it, some entrepreneurs nevertheless were willing to perform asbestos
abatement in exchange for the promise of a hefty profit margin.
Overall there is a lack of standards for those who design,
perform, and monitor asbestos abatement projects.
Environmental consultant. Other than training courses and
certifications required by the federal, state, and local governments, the
threshold knowledge, training, and experience of those who design and monitor
abatement projects varies widely. The environmental consultant may range from
the very inexperienced hygienist to the seasoned engineer.
Although it may be possible to tell the difference, even
seasoned owners will have trouble distinguishing among different levels of
experience, education credentials, and price. As discussed in Section 13.7,
it is clear that a lack of standards leads to unevenness when it comes to
estimating the asbestos abatement project or even developing a consistent
understanding of what is involved in the project.
Asbestos abatement contractor. There is simply no
standardization of credentials that helps the owner choose an asbestos
abatement contractor. Often the owner will simply advertise for bids and
award the project to the low bidder.
Due to health and safety concerns unique to environmental
work, it is imperative that careful underwriting be done before an asbestos
abatement contractor is chosen. Although at one time it was difficult to
ascertain the track record or stability of a company, this should no longer
be the case.
There are many distinctions that go beyond the basics. The
basis for comparing abatement contractors may be their dissimilarities. Some
began as insulation contractors, demolition contractors, general contractors,
or drywall or carpentry contractors. Some started with absolutely no
background in construction.
A complicated renovation project involving abatement
requires an abatement contractor with an in-depth background in demolition
and drywall work. In an abatement project involving removal of asbestos pipe
covering which is to be followed by recovering, an abatement contractor with
experience in insulation work may be best. Certainly, the estimate should be
more reliable if the abatement contractor is aware of the next step. It may
also serve the owner to award the drywall work to the same contractor.
Owner. The disparity in environmental consultants and
contractors is magnified by the disparity among those owners who hire them.
Of course, there is no conceivable guideline for ownership of property. There
are those owners who will operate with absolutely no regard for health,
safety, and environmental matters because of ignorance, concern for the
bottom line, or other reasons.
Developing a list of credentials including education,
industry experience, representative clients, and violations (or lack thereof)
for each of the three entities discussed - owner, environmental consultant,
and abatement contractor - should help determine whether a project will face
a differing site conditions claim.
The profile of the owner may be the most enlightening and
the hardest one to compile, as the owner is not bidding on projects or
marketing its abilities to manage a facility. Following is a list of relevant
questions to answer about the owner and its premises:
- Are there accurate and up-to-date as-built drawings of the
premises?
- What are the qualifications, experience, and training of
the managers of the facility? What is the level of staffing?
- Is the facility to be abated in good physical condition as
to long-term maintenance? Is it clear of debris? Are the elevators in good
working order? Are there staging areas for abatement work? Are there
elevators that will be available for use during the project? What is the
condition of the electrical system? Is there an ability to turn off or
disconnect the electricity during asbestos abatement work?
- Is the owner or are the facilities managers forthcoming in
answering questions? Are they responsive and cooperative on the walk-through?
With built-in complications inherent in the asbestos
abatement process and a wide disparity among the participants, it is no
wonder that there are few asbestos abatement projects without a basis for
some differing site conditions claim.
Section 13.3 Factors Leading to Claims
The prevalence of subjective factors in asbestos abatement
work leads to differing site conditions claims. Determining what the
experienced, prudent contractor would have known is hard to judge.
Probably the worst case scenario is one in which the owner
is unsophisticated, is looking to cut corners, and therefore hires only a
minimal amount of consultant assistance and aims to retain a
"cheap" contractor. In this instance, consultant assistance and
aims to retain a "cheap" contractor. In this instance, it is an
open issue as to what constitutes a changed condition. The contractor walked
onto the job without a clear delineation of what the conditions were at the
premises because the consultant was only paid a minimal amount to draw up the
abatement plan and to allow the owner to merely comply with regulatory
requirements. Subject to contract provisions and the provable state of
knowledge of each of the parties, virtually every unknown in this case turns
into a differing site conditions claim for the contractor.
Differing owner knowledge is critical and may be as
follows:
- The owner knows and the contractor does not know of the
condition: when the condition is encountered, the owner must pay the
contractor, even in the face of an exculpatory clause.
- The owner does not know and the contractor does not know
of the condition: when the condition is encountered, the owner will have to
pay unless there is an exculpatory clause that provides otherwise.
- Variations of these circumstances occur when the owner
should have known or the contractor should have known.
Although differing site conditions claims in asbestos
abatement are most closely associated with changes in perceived conditions at
the site, changed conditions can relate to factors other than those
immediately at hand.
Regulatory environmental changes. As environmental
regulations change rapidly, the cost of performance of asbestos abatement
work can be dramatically altered midstream. The vigor or the prevalence of
enforcement of existing laws and regulations can also change, increasing the
cost of performance. An example is a regulatory requirement that a contractor
use transfer stations for the asbestos waste, assuming that the requirement
was not being enforced at the time of the contract signing but is being
enforced at the time of performance. If the fee of the transfer station was not
included in the bid, it is not clear whether the contractor will be able to
get the owner to pay. A careful review of contact clauses and the knowledge
of each party will have to be made.
Changes in availability of waste disposal sites. Localities rebelling against taking disposal of environmental waste and
limited capacity of disposal sites may lead to a dramatic and unexpected
increase in cost to the contractor for disposal. This eliminates the
contingency that the abatement contractor will build into the bid to cover
the risk of liability or unexpected cost increases attendant to disposal of
asbestos waste.
Changes in labor arrangements. Labor relations can always
cause problems in the construction industry, and asbestos abatement projects
are no different. There is no perception that because the trades performing
abatement work operate under the cover of darkness (often literally at night
or on weekends or inside containment areas) and they often are on and off the
project before following trades arrive, they can use nonunion labor on an
otherwise union project.
If this is discovered, there will often be pressure on the
owner to make sure that the abatement contractor uses union labor. Most often
the standard construction contract includes a clause making the abatement
contractor responsible for harmony of labor relations, and the contractor
will be forced to pay additional increments due for union labor.
Although owners have been known to be sympathetic to the
plight of the contractor in this circumstance, concessions will most often be
voluntary and only partial. Other owners may justifiably believe that the
contractor's assumptions in estimating labor for a lump-sum bid are not the
owner's concern. Although there are contractors who disagree, this is not a
true differing site conditions claim.
Negative air patent restrictions. Those in the asbestos
abatement industry must be aware that GPAC, Inc. licenses contractors to use
the patented negative air system. The patent provides a broad scope of
protection for asbestos abatement using the application of negative pressure
and filtration of air by the use of negative air machines. Since its issuance
in 1986, the patent has repeatedly been challenged and issues contesting the
validity of the patent are currently pending before federal district courts
in North Carolina, Delaware,
and Washington, D.C. In an effort to enforce its patent,
GPAC, Inc. has embarked on a campaign to force contractors to obtain a
license before employing the system. It has also notified building owners and
even consultants about the existence of the patent. In order to protect
themselves, Mississippi and New Jersey have
implemented policies requiring that bidders either hold a license from GPAC
or agree to indemnify the public entity from any potential infringement
claims.
Until the courts determine the validity of the patent,
contractors, builders, and consultants must remain wary. In order to minimize
potential liability from patent infringement claims, legal counsel should be
sought in drafting bids and contracts involving asbestos abatement.
Patent requirements. With the issue of the GPAC patent
having been contested in the courts, its importance cannot be minimized. If
the contract is signed without any regulatory or contractual responsibility
for use of patented equipment, will the contractor prevail in its attempt to
recover for the cost of complying with the license fees to use the patented
equipment if the holder of the patent requires it after the date the contract
is signed? Is the answer affected if the patented equipment must be used to
comply with regulatory requirements? Is the answer affected if the patented
equipment is not required by regulators but the use of any other acceptable
method will cost the contractor double the money?
It seems appropriate that if the design calls for a
proprietary item to be used and it has not been disclosed that the item is
patented, the contractor should not be required to bear the cost of defending
a lawsuit and paying a settlement or judgment in relation to an infringement
suit or for additional license or royalty fees. However, if the contractor
has utilized a patented item on its own, then the contractor might be
expected to bear that cost.
The contractor should indemnify and hold harmless and pay
the cost of defense of the owner and environmental consultant if they are
sued for patent infringement when the contractor has chose the patented
equipment.
Owner interference. The asbestos abatement project is
especially susceptible to disruption and massive additional cost if the owner
does not fully cooperate and "clear the way" for the contractor's
performance. The failure of these obligations may be considered a changed
condition entitling the contractor to be paid more. Some of the owner's
shortcomings in this area include:
- Failure to provide access. This may be particularly costly
even in the short term, and the owner's responsibilities may be significant.
For example, the owner may have been required to provide contractor access to
tenant space by providing notice to tenants to vacate their space during a
weekend or after-hour period when the contractor would be working. If the
contractor shows up but the owner forgot to notify tenants and the contractor
is not able to work that night or that weekend, the cost could be very
considerable.
- Decision making of the owner/consultant. If the
decision-making process of the owner or its consultant is slow and holds up
the contractor's performance, the contractor could be entitled to
compensation. This is particularly the case when the contractor is working
overnight or over a weekend and is unable to reach a representative who is
authorized to make a decision.
- Use of elevators. If the contractor's bid is predicted
upon using the elevators and the stairways must be used to carry out debris,
this may entitle the contractor to be paid more. This issue should be
addressed pre-bid.
- Water supply. If the contractor is promised in the
contract that it will be allowed to use water supplied by the owner and then
is required to run temporary water lines, the contractor may be entitled to
additional payment.
- Electricity. In a fairly common problem in renovation and
abatement, before the abatement is undertaken, it is assumed that the
building power can be used for the contractor's equipment. If once the job is
begun the power must be shut off, the contractor may be entitled to
compensation for supplying temporary power and power lines. The abatement
contractor may be the one to discover this, as it is the first one with
access to the site. This must be addressed in the contract.
- Use of staging areas. Of paramount importance on the
abatement project is where the asbestos that is being removed can be placed.
If there is no temporary staging area, cost implications could be severe.
- Failure to provide information. When the bid documents
provide that the contractor will be given "as builts" of the area
being abated, the failure of the owner to do so may later bring about a claim
by the contractor for additional compensation. It would appear that the
failure to provide consultant reports when they have been promised may also
lead to a claim for changed conditions.
Section 13.4 Contract Clauses: How They Can Help or Hurt
The quality of the contract documents, from the
boilerplate to the significant business terms to the technical
specifications, really sets the pattern for the project. The abatement
project, especially a costly one done under tight time constraints,
demonstrates the huge dollar amount attributable to each misstep in contract
documents.
If the owner makes an improvident choice in environmental
consultants, the owner may end up paying for that poor choice over and over:
in price, in schedule, and in lost revenue when the project does not get
completed on the following clauses should be included in the business terms
of the contract documents and carefully tailored to the project time.
The qualified and experienced environmental consultant
will see to it not only that the contract documents protect the owner, but
also that the owner has attended to the basics and that the contract
documents are clear to the bidders. This approach should provide (1) a way of
obtaining the best bids for the owner, as the contractors will not be
required to build in a contingency for potential misunderstandings in scope
or intent, and (2) protection against being required to pay differing site
conditions claims later.
Scope of work. There is no doubt that the scope of work clause
is the most important clause. It is clearly within the capability of the
environmental consultant and the owner to draft this clause properly if they
have done an adequate investigation of the site before writing it.
The owner can make foolish choices and use the scope of
work clause as an attempt to prevent the contractor from getting paid for
changed conditions if they are encountered. An example of such a clause is:
The Owner's Consultant has prepared a survey report which
has been delivered to the Contractor. The Contractor acknowledges that the
survey report has been received and reviewed. The Contractor shall remove all
Asbestos Containing Material in the building. The Consultant's survey report
is dated August 17, 1991 and identifies the Asbestos Containing Material
anticipated to be encountered.
This clause causes trouble because it intends to obligate
the contractor to take responsibility for asbestos removal beyond that which
may have been contemplated by the consultant or the owner. It would appear to
take the pressure off the consultant or owner to have found the areas where
the asbestos existed.
It is likely that the court would construe this clause
against the owner, especially if the asbestos is found in a wholly different
area of the building than that shown on the abatement plan. However, the
contractor should not feel comfortable relying on the equity of a court or
the owner when seeking to obtain additional deserved compensation.
The good scope of work clause, together with well-defined plans
and specifications, does two things:
- It locates, describes, and quantifies all
asbestos-containing material (ACM) in the building or facility.
- It identifies the response action required to be taken for
each item of ACM so designated.
Compliance with all laws. Defined correctly, a change in
laws, regulations, or their enforcement, after a lump-sum asbestos abatement
project has begun, will be deemed a differing site condition for which the
contractor will receive additional compensation. Defined improperly, any such
change will be a cost the contractor must bear.
A standard clause that is not helpful states:
The Contractor shall give notices and comply with all
applicable laws, ordinances, rules, regulations and lawful orders of public
authorities.
In order for the contractor to be protected by the clause,
the following language must be added: "in effect and being enforced at
the time of the signing of this agreement."
Sequencing of the work, suspension and damages for delay.
Lump-sum contracts for asbestos abatement may also include the following
troublesome clauses:
The Contractor shall perform the Work in such order and
sequence as directed by the Owner or the Owner's Consultant.
***
The Owner may, without cause, order the Contractor, in
writing, to suspend, delay or interrupt the Work in whole or in part for such
period of time as the Owner may determine.
***
The Contractor agrees to make no claim against the Owner
for damages for delay or interference in the performance of this Agreement
occasioned by any act or omission to act of the Owner or any of its
representatives or for any other cause whatsoever, and agrees that any such
claim shall be fully compensated for by an extension of time to complete the
Work as provided herein.
On the asbestos abatement project, there can be no doubt
that signing an agreement containing these clauses gives the owner carte
blanche to disrupt, fail to give information, and fail to follow up on
information and decision making. If faced with a decision as to whether to
sign or lose the opportunity to do the job, it may be best to forgo the job.
If a contractor does sign a lump-sum contract with these clauses, it may lose
a substantial sum when a differing site condition arises.
Contractor obligation to visit site. Many contracts
contain a clause stating that the contractor has visited the site, has
examined it before placing his bid, and is fully familiar with it. This type
of clause may rule out a differing site conditions claim, although the courts
will surely construe it against the owner if given the opportunity to do so.
If the contract is negotiated, this clause should be clarified.
What is not clear is whether the contractor's inspection
of the site includes any destructive testing or taking of samples. The clause
should state the nature of the actual examination undertaken or required to
be undertaken.
Differing site conditions clause. The following site
investigation clause indicates that the full risk of a changed condition is
on the contractor:
The Contractor represents that it has had the opportunity
to examine and has examined carefully the plans and specifications and the
contract and has acquainted itself with the conditions of the Work site: and
that it has made all investigations essential to a full understanding of the
difficulties which may be encountered in the performance of the terms of this
agreement. The contractor will, regardless of any such conditions which may
exist at the site of the project or its surroundings, assume complete
responsibility for completion of the project under any such conditions which
may exist at the site of the project or its surroundings and all risks in
connection therewith. In addition thereto, the contractor represents that it
is qualified fully and able to complete the project in accordance with the
terms of the contract and within the specified time.
On the other hand, paragraph 4.3.6 from the AIA General
Conditions of the Contract for Construction, AIA Document A201, 1987 edition,
specifically allows for recovery for changed conditions claims.
When no asbestosis anticipated. Article 10 of AIA Document
A201's General Conditions of the Contract for Construction, 1987 edition,
includes a series of provisions that attempt to place the responsibility for
detecting and dealing with asbestos on the owner.
The Engineers' Joint Contract Documents Committee (EJCDC)
Standard General Conditions of the Construction Contract 1910-8 (1990) goes
further than the AIA in affording protection to the contractor who does not
anticipate finding asbestos. The applicable provisions read:
- OWNER shall be responsible for any Asbestos, PCBs,
Petroleum, Hazardous Waste or Radioactive Material uncovered or revealed at
the site which was not shown or indicated in the Drawings or Specifications
or identified in the Contract Documents to be within the scope of the Work
and which may present a substantial danger to persons or property exposed
thereto.
- CONTRACTOR shall immediately: (i) stop all Work in
connection with such hazardous condition and in any area affected
thereby.CONTRACTOR shall not be required to resume Work in connection with
such hazardous condition or in any such affected area until after OWNER has
obtained any required permits related thereto and delivered to CONTRACTOR
special written notice.
- If after receipt of such special written notice CONTRACTOR
does not agree to resume such Work based on a reasonable belief it is unsafe,
or does not agree to resume such Work stoppage under such special conditions,
then Owner may order such portion of the Work that is in connection with such
hazardous condition or in such affected area to be deleted from the Work.
Section 13.5 Avoiding Differing Site Conditions Claims
The primary way that an owner can avoid differing site conditions
claims is not by drafting a better contract or hiring a better lawyer, but by
doing its job better. The effect of a changed condition on the progress and
cost of an abatement project may depend upon the owner's asbestos management
philosophy. One of the most compelling arguments in favor of total asbestos
removal is that it eliminates potential lawsuits and shields against future
exposure. Although medical risk from low-level exposure may be extremely
small, it is not nonexistent, as there is no minimum threshold for
mesothelioma,an asbestos-associated cancer of the mesotheliam or chest cavity
lining.
Although a worker who mined, manufactured, or installed
asbestos is open to significantly greater risk, office workers' lawsuits are
more than just a theoretical possibility. In Layne v. GAF Corp.,(4) an
officer worker who was employed from 1973 to 1985 as a word processor in a
federal office building containing asbestos recovered from an asbestos
manufacturer after she developed mesothelioma.(5)
Section 13.6 Analysis of Damages
Differing site conditions claim analysis and litigation,
because it most often does not derive from a clear record, relies on careful
review of contemporaneous records and the testing of witnesses' memories.
Both liability and damages issues are decided in this fashion.(6)
Before the work begins, it may be possible to determine an
acceptable formula by which the contractor will be paid if it is to remove
more asbestos than is anticipated by the original contract or if the project
is held up and the contractor, while doing the same work, will have to be at
the job for longer. These suggestions apply to any construction project but
become more essential in the asbestos abatement context because of the speed
at which the contractor is working and the significant amount of labor
expended each day.
The acceptable unit prices should be placed right in the
contract so the parties can avoid the wrenching process of computing costs if
doing so becomes necessary.
Types of damages the parties should be concerned with
include:
- Labor (extended, additional, idle, or escalated)
- Material (additional or escalated)
- Supervision in the field (field overhead) (extended or
escalated)
- Supervision from the home office (home office overhead)
(extended, additional, idle, or escalated)
- Equipment (extended, idle, or escalated).
If there is no predetermined unit price, it will be
necessary to review records that show the increased costs of performance of
the work and impact costs for the delay and disruption of other work
activities resulting from the condition.
The records that must be reviewed are those showing the
extent and rate of production for work activities affected by the condition
and documenting crew and equipment usage in performing the work.
The factual confusion that can result from an asbestos
differing site conditions claim is illustrated in Universal Contracting &
Brick Pointing Co. v. United States.(7) In the Universal case, the court
found that material issues of fact precluded summary judgment on the
contractor's claim for extra compensation on (1) the claim that the owner
furnished defective specifications; (2) whether presence or asbestos and glue
constituted differing site conditions; and (3) whether the owner had superior
knowledge of presence of asbestos and glue in the paint system.
Count III of the contractor's complaint alleged that, in
performing the contract, the contractor encountered asbestos on the exterior
walls of the buildings, which constituted a differing site condition under
the terms of the contract, and that this condition was not discoverable
through a reasonable site inspection.
The contract contained a clause covering differing site
conditions, which stated in relevant part:
- The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writing of:
- subsurface or latent physical conditions at the site
differing materially from those indicated in this contract, or
- unknown physical conditions at the site, of an unusual nature,
differing materially from those ordinarily encountered and generally
recognized as inhering in work of the character provided for in this
contract.(8)
The contractor claimed that the presence of asbestos in
the buildings satisfied the elements of either differing site condition
category. With respect to category 1, the contractor argued that the contract
documents indicated that the contractor would be required to remove paint,
not asbestos, in performing the contract, and that the contract gave no indication
that such a latent physical condition as asbestos would be encountered
beneath the layers of paint. The contractor contended that the site
conditions, as indicated at several places in the contract documents, gave
rise to a permissible inference that only paint would be encountered during
contract performance.
With regard to category 2, the contractor argued that
asbestos is not a material ordinarily encountered in paint removal contracts,
and that no other contractor at the site encountered this type of material
In Owners Realty Management Construction Corp. v. Board of
Education,(9) at the request of the architect and assistant supervisors, the
contractor, under protest, removed asbestos in the owner's schools from areas
the contractor claimed were outside the scope of the contract.
The contractor's summary judgment motion was denied
because there were triable issues of fact as to whether the work ordered by
the owner's representatives constituted such an extraordinary demand that
there "could be no reasonable doubt that [the demand] exceeded the
obligations of the contract and that a refusal to comply with it would not
work a breach of contract."(10)
The court concluded that the asbestos removal performed by
the contractor at the owner's representatives' directions was "so
preposterous, so manifestly beyond the limits of the agreement, as to suggest
a threat to the public interest."(11)
In a 1990 case, a contractor was performing under a
temperature and humidity control contract for rehabilitation work in the main
branch of the New York Public Library at Fifth Avenue and 42nd Street in Manhattan. Eight months after work began,
the owner (the city of New York)
for the first time said that the insulation surrounding some existing piping
and ductwork was composed of hazardous asbestos, which would have to be
removed.(12)
After extensive negotiations and correspondence, the
contractor refused to undertake the work in compliance with a change order
issued by the city because the work to be completed pursuant to the change
order exceeded the 5-percent limit,(13) funding had not been approved, and
the city would not hold the contractor harmless from any asbestos-related
claims.
The city defaulted the contractor. The lower court held
that the contractor was in default and that the surety had waived the claim
that the asbestos removal change order constituted a material change of the
contract by negotiating the price of the work with a subcontractor and
submitting an estimate of the cost of the work on the change order.
The appellate court decided that the contractor and surety
could relitigate the default and were not barred by res judicata for the
default proceeding.
Tuscaloosa City Board of Educ. V. American/Owens, Inc.(14)
involved litigation over the method of dispute resolution. Under the
contract, American/Owens agreed to remove asbestos-containing material from
buildings owned by the board of education for a lump sum, subject to
additions and deductions provided for in the contract.
The contract provided that "any dispute, claim or
question concerning the interpretation of meaning of the Contract Documents,
or concerning a breach of the Contract, shall be submitted to the Director
and his decision shall be final and binding on the parties to the Contract."(15)
After beginning the work, American/Owens reported to the
board that the quantity of asbestos to be removed from the buildings exceeded
the amount it expected to find based on drawings and specifications made by
the architect employed by the board, and that the work would be done as an
extra item not within the contract.
When the board refused to pay for extra work, a hearing
before the director of the State Building Commission was convened, at which
the board argued the director lacked jurisdiction to resolve the controversy.
Thereafter, the director entered an order requiring payment of the additional
amount demanded by American/Owens.
The board filed a declaratory judgment action, claiming
that the dispute was not subject to resolution by the director on the basis
that only disagreements over "contract provisions" were within the
settlement authority of the director.
The court found the contract provisions to contain
inconsistent or unclear provisions that the arbitrator interpreted in resolving
the dispute. These contract provisions are worthy of note here as a lesson
for owners who wish to avoid a costly dispute resolution process by focusing,
up front, on contract drafting. The contract provisions were:
Scope of Work
The contractor will be responsible for the removal of all
friable asbestos in student occupied areas, including, but not limited to,
that covered in the base bid. In the event there is a question as to whether
material is friable, or whether the area is student occupied, the architect/engineer
will make the final decision.
***
Changes in the Work
The Owner may at any time make changes in the Work by
changes in the Drawings and Specifications of the Contract and within the
general scope thereof. Changes will be in the form of a Contact Change Order
based upon a written request of the Owner and a written proposal of the
Contractor. All Change Orders will require consent of Surety by endorsement
of the Change Order form. In making any change, the charge or credit for
altering, adding to or deducting from the Work shall be determined by one of
the following methods selected by the Owner:
***
Claims for Extra Cost or Extra Work
If the Contractor claims that any instructions by drawings
or otherwise are not in accordance with the Contract Documents, and involve
extra cost under the Contract, he shall give the Architect and the Director
written notice thereof within ten (10) days after receipt of such
instructions, and in any event before proceedings to execute the work and the
procedure shall then be as above under [the Changes in Work section].
Otherwise no claim will be considered.(16)
The case of Castle Construction Co./Tuskegee Lumber Co. v.
Owens & Woods Partnership(17) demonstrates the treatment of the
encountering of asbestos after a renovation has begun.
Castle Construction Company/Tuskegee Lumber Company
(Castle) entered a contract to renovate and modernize the Central City
Housing Project in Birmingham,
Alabama, owned by the Housing
Authority of the Birmingham District (HABD).
Castle suspended work when unanticipated asbestos was
encountered in each of the buildings being renovated. Castle advised the
architect that delay would result. The architect responded by changing the
project specifications to provide for the asbestos removal, and the owner,
the architect, and the contractor agreed to two change orders that afforded
the contractor with the direct costs of the asbestos removal.
After the completion of the project, the contractor
presented a claim for delay costs suffered in addition to the direct costs
for the asbestos removal. When HABD denied the claim, the contractor sued for
breach of contract.
The contractor sought increased costs it suffered as a
result of the asbestos-related delay, plus similar costs its subcontractors incurred.
The court stated:
The discovery of asbestos was clearly a 'latent defect' as
defined in the contract, and the change orders entered into between HABD and
Castle compensated Castle and its subcontractors for the additional labor and
materials required for its removal. Accordingly, we also hold that Castle is
not entitled to delay or disruption damages from HABD or Owns and Woods on
behalf of its subcontractors.(18)
The contract provisions in this case were as follows:
Changes in the Work
8(b) Any change in the work shall be ordered and the
adjustment of the contract price or time shall be determined by one of the
following methods: Method 1 - Adjustment before Performance.Method 2 -
Adjustment after Performance.The Contractor shall keep an accurate current
account of such work and present it in such form, and substantiated by such
supporting papers as the Architect may require. Upon completion and
determination of the cost, a Change Order shall be issued establishing the
increase or decrease in the contract price or contract time.
8(e) The cost shall include all direct and necessary
production costs of the work itself.
9(b) Should the Contractor encounter subsurface or latent
conditions at the site materially differing from those provided for in this
Contract, or unknown physical conditions differing from those inherent in
work of the character provided in this Contract, he shall promptly, and
before such conditions are disturbed, notify [the Owner] in writing.
9(e) If, on the basis of available evidence, [the Owner]
determines that an adjustment of the contract price or time is justifiable,
the procedure shall then be as provided herein for 'changes in the work.'(19)
Section 13.7 Strategy for Contract Administration and
Claim Management
Owner's Strategy
The owner's claims prevention and claims management
strategy must start on the first day of ownership of the building. The owner
must develop a comprehensive plan to manage asbestos. The owner's asbestos
management program, if set up properly, becomes the owner's contract
administration and claims management program. Whenever a move is made in the
interior of the building containing asbestos which is being maintained in
place, the owner's overall asbestos management plan must be consulted.
In developing an asbestos management policy, owners should
follow these 10 steps:
- Take a detailed inventory of all asbestos in the building,
its condition, and what is being done about it. Keep this inventory updated,
and make sure it is reviewed before any renovation is undertaken. If sued,
the building owner is not "off the hook" merely because the owner
did not know of an asbestos problem; the building owner is held to the
standard of "what a reasonably prudent owner in the locality should have
known under the circumstances."(20)In current terms, there is much the
owner "should have known" about asbestos.
- Once an inventory shows the presence of asbestos, prepare
a written operations and maintenance (O&M) plan, and make sure that all
relevant personnel are familiar with it. Make sure that the O&M plan is
kept up-to-date.
- Hire a facilities management staff carefully and make sure
they are fully aware of all aspects of asbestos maintenance and removal. Make
sure they attend formal training on an ongoing basis.
- Set up a consistent and well-organized recordkeeping
system relating to asbestos management, and monitor it to assure that it is
being followed.
- Formulate a written plan for addressing emergencies
relating to in-place asbestos (such as a burst heating pipe or a water leak),
and make sure that facilities management personnel are fully trained in these
procedures. It is important that emergencies be addressed promptly and
thoroughly and that proper contemporaneous documentation be kept. The 24-hour
phone numbers of the asbestos management team should be made available to
facilities management personnel and executive level personnel and the owner's
engineer, lawyer, and publicist. It is important that a chain of command be
identified and that a coordinator be appointed for this important function.
- Develop a hands-on program; know firsthand the quality of
the asbestos management program. Do not rely solely on the advice of others.
If you are an owner or an executive of the owner, know all of the facts and
ask questions.
- Do not rely on insurance. Expense, policy limits, sunset
clauses, exclusions, the claims-made nature of coverage, the long-delayed
manifestation of asbestos-related liability, and questionable long-term
stability of insurance companies preclude such reliance. If an abatement is
being conducted, make sure that the contractor obtains asbestos coverage on
an occurrence basis from a stable and rated insurer.
- Do not rely on contract clauses that purport to provide
protection. Indemnity clauses or other assurances provided by prior owners,
abatement contractors, transporters, or others are only as good as their
future solvency. However, even though it is not a complete answer, make sure
that proper protection is obtained when a purchase, sale, or lease is entered
or when an abatement contractor is hired.
- Worry about where removed asbestos is being disposed. If
the asbestos is removed and improperly disposed, the owner may be sued to
clean up the
The Science Magazine article, in its section entitled
"Public Policy," stated:
The available data and comparative risk assessments
indicated that chrysotile asbestos, the type of fiber found predominantly in U.S. schools
and buildings, is not a health risk in the non-occupational environment.
Clearly the asbestos panic in the U.S. must be curtailed,
especially because unwarranted and poorly controlled abatement results in
unnecessary risks to removal workers who may develop asbestos related cancers
in later decades.(26)
Based on this information, these headlines appeared:
"Study Opposes Removal of Asbestos"
"Health Risks of Asbestos Downplayed"
"Risk Is Seen in Needless Removal of Asbestos"
"Health Experts Say Billions May Be Wasted by
Removing Banned Insulation Material"
The building owner should not change the long-range
asbestos policy set out in the "Ten Asbestos Commandments." Unless
asbestos has become airborne through use or one is about to disturb it, there
is no requirement that an owner remove it. In fact, the Environmental
Protection Agency (EPA) has issued guidelines encouraging owners to set
strategies to manage asbestos in place by using operations and maintenance
(O&M) plans.(27)
Probably imprudently, "in-place" legislation,
which would have required asbestos inspections in buildings, was shelved,
locally in cities such as New York,
and in Congress. These laws did not require removal of asbestos. Their
purpose was to "create a level playing field" for building owners
and to endorse a "responsible asbestos policy" to which owners
should adhere. They would simply have required that the buildings be
inspected to see if there was an asbestos problem, and if there was a
problem, that a solution be formulated and implemented.
Note that when a 1988 study was conducted by the city of New York of 900
buildings there, 84 percent had asbestos in poor or fair condition. Whether
there is a statutory requirement or not, the building owner is responsible
for properly managing the asbestos in place or for removing it. The study
further showed that two-thirds of all buildings in New York City contained asbestos containing
Section 13.8 Alternative Dispute Resolution Contractor's
Strategy
The contractor's strategy, of course, is not set from a s
early a point as that of the owner. Although the owner has been able to plan
and prepare its approach from the time the building was owned, the contractor
most often starts planning at the time it bids on the contract. Most often,
the contractor is not able to set the contract terms and may not, in the case
of a sealed bid, be able to negotiate them. In addition, there may be a
number of clauses that will prevent the implementation of a successful
strategy for obtaining prompt payment on a differing site conditions clause.
The contractor's leverage is never greater than when the
owner needs the contractor. The owner needs the contractor before it has
fully performed and before it becomes easy to kick the contractor out and
bring in another one.
It is clear that the clause requiring the contractor to
keep working while a dispute on changed conditions is resolved is harmful to
the contractor's leverage rights. If the owner must face a situation in which
job progress is affected, the owner will "light a fire" under the
contractor because the contractor will be in default and the owner will be
able to bring in a replacement if the contractor fails to continue.
Leverage is a tricky mechanism, and it is not a good part
of contractor strategy for the contractor to walk off the job or to suspend
work in the face of a clause that calls for its continued work during the
resolution of a dispute.(31) If enough money is involved, there must be an
interim solution of some sort if the contractor is to keep meeting
payroll.(32) Perhaps there is a way for the contractor to obtain payment to
the extent the owner feels appropriate and to reserve the right to sue for
the rest later. It is to be expected that if an interim payment is to be made
by the owner, that the owner will expect a full release for that item; that
is the owner's use of his leverage - after all, the contractor needs the
payment now and maybe to get it he will take less.
Section 13.8 Alternative Dispute Resolution
Many differing site conditions claims involving management
of asbestos have been settled without resort to litigation, perhaps because
of both owners' and contractors' relative inexperience in asbestos abatement.
The reason could, of course, simply be that owners would prefer not to see themselves
locked in disputes over their environmental problems in a public forum.
The 1980s saw the passage of a massive volume of new
asbestos-related legislation and regulations and the development of common
law doctrines that broaden existing areas of legal responsibility relating to
asbestos.
As a result, for the 1990s, the federal and state courts
are in for an onslaught of new cases, including asbestos changed conditions
cases. Many of them, in volume of documents, complexity of legal and factual
issues, number of witnesses, and number of parties involved, will resemble
antitrust, construction contract, and other large and protracted commercial
litigation that already confounds the courts.
Clearly, the alternatives to the time-consuming and costly
conventional means of dispute resolution may be welcome in this heavily
regulated industry. Alternative dispute resolution (ADR) has been used with
great success in commercial and contractual disputes.(33) It is clear that
with the heavy docket of the courts, commercial litigation will take many
years to reach trial, although 90 to 95 percent of all lawsuits are settled
before trial. The goal, then, must be to replicate, at an earlier stage, the
same types of dynamics that are present on the courthouse steps.(34)
Proponents argue that ADR has many advantages:
- It accelerates the dispute resolution process, which
allows the parties to focus on their interests rather than on the procedural
strategy of the case, and provides "a day in court," allowing for
advocacy and emotional outlets.
- It assures the involvement of executives early in the
process.
- It avoids the need to educate a judge or jury.
- It can better protect confidentiality.
- It avoids acrimony that often accompanies litigation and
allows for business relationship between the parties to continue.
In a situation in which the parties enter a contract with
each other, such as one between an owner and asbestos abatement contractor,
it is appropriate to specify, in the contract itself, the procedure under
which any disputes between the contracting parties are to be resolved. Even
though some parties feel there could not possibly be a problem and are
unwilling to give attention to the inclusion of an ADR clause in their
agreement, others, who have seen the economy created through the use of ADR,
are now including ADR in the contract documents.
Certainly it is never too late to use ADR at any point,
especially in cases that have been at an impasse after a number of years of
traditional litigation. Impasse can arise from personality conflicts between
counsel, poor communications between parties, inflexible negotiating
postures, or difficult policy or internal political reasons.
The parties can rest assured that the court will encourage
their use of ADR. In fact, the courts have increasingly suggested resort to
ADR, especially in connection with technically complex issues that the court
is ill suited to address.
In contractual relationships, the method of dispute
resolution can be a point of negotiation along with the other terms of the
agreement. Approaches to certain recurring problems can be fashioned (such as
scope of work disputes, evaluation of undisclosed conditions claims, and
interpretation and application of government regulations).
There appears to be no single universal process that will
work for every dispute. A number have been used, including:
- Mediation: Facilitates settlement by use of a neutral
party who has no power to make binding decisions, but who may schedule and
structure negotiations, act as a catalyst between the parties, focus the
discussions, aid communications, and serve as an assessor and not a judge of
the positions of the parties.
- Arbitration: Employs a neutral party to hear all or a
portion of the factual, legal, or policy issues in a case and make binding
decisions. Arbitration is generally less formal than court proceedings, as
discovery is, in theory, severely restricted and the rules of evidence are
not strictly followed.
- Fact finding: Uses a neutral third party with industry
expertise to narrow factual issues. The process can be either binding or
nonbinding, and the parties, if they so choose, can treat the decision on the
issues of fact as admissible in subsequent proceedings.
- Minitrial: Permits parties to present their cases (or
portions of their cases) to principals who have authority to settle the
dispute. Following the presentation, the principals continue negotiations
with the aid of the third party who has acted as the minitrial judge.(35)
- Settlement judge: Involves the participation of judges of
the court hearing the case who are not involved in any aspect of the
litigation. The settlement judge hears the positions of the parties and
offers suggestions as to the reasonable compromises in light of the judge's'
evaluation of likely outcomes.
- Summary jury trial: Involves an abbreviated trial before a
jury assembled by the parties to get a sense of the amount likely to be
awarded after a full trial. The decisions of the summary jury are advisory
only.
No matter what type of lawsuit is at hand on an asbestos
abatement project, it is likely to include the analysis of voluminous
technical evidence. Therefore, exploration of ADR is wise. The alternative is
waiting years for a resolution, with perhaps the same result, after expending
tens and perhaps hundreds of thousands in attorneys' fees and court costs and
an equally large amount of time. Under these circumstances, ADR becomes an
attractive option.